Susquehanna Health Facility Redevelopment Project

"Project 2012"


Susquehanna Health launched a major initiative in 2006 to redevelop its current campus locations with new and updated facilities that will give our patients the excellent care they have come to expect from Susquehanna Health. The objective of the entire redevelopment project is consistent with our mission, vision and values and affords contemporary "best practice" medical care in a safe, efficient, flexible and aesthetically pleasing environment that is conducive to health and healing.

Facility Update - 06/25/08

Divine Providence Hospital

  • Preliminary work on the main entrance canopy begins June 23. Barricades and signs will be placed in this area to redirect pedestrian and vehicular traffic.
  • The week of June 30 the existing canopy will be demolished & the Healing Garden is expected to be complete.
  • The Williamsport Hospital & Medical Center
  • The Energy Service Center foundation slab will be poured July 2 - 4.
  • Planning continues for the temporary ED entrance along Walnut Street.
  • Bostley's Day Care construction continues.
  • Design development continues for the Patient Tower.